How to Report a Hazard

  • Member or Admin access to SteadyOn
  • The location, description, and rough risk level of the hazard

  1. Click Hazards in the sidebar
  2. Click Report Hazard
  3. Enter a clear Title that describes the hazard — for example, Exposed electrical cable near server room door
  4. Add a Description with enough detail for someone unfamiliar to understand the hazard
  5. Enter the Location where the hazard exists
  6. Set Hazard Type:
    • Permanent — the hazard will exist until actively removed
    • Temporary — the hazard is short-term (e.g., during construction work)
  7. Complete the Risk Assessment:
    • Set Likelihood — how often is harm likely to occur?
    • Set Consequence — how severe would the harm be?
    • SteadyOn calculates the Risk Level automatically
  8. Enter any Control Measures already in place
  9. Set a Review Date — when should this hazard be reassessed?
  10. Assign a Responsible Person who owns this hazard
  11. Click Save Hazard

For a more guided experience — useful for workers who are less familiar with risk assessment — use the Guided Wizard:

  1. Click More ▾ in the Hazard Register header
  2. Click Guided Wizard
  3. Answer the questions in plain language

The wizard translates your answers into a full hazard record with a risk assessment.


If you have an existing hazard register in a spreadsheet:

  1. Click More ▾Import CSV
  2. Download the CSV template
  3. Fill in your hazards (one per row) and save as CSV
  4. Upload the file — SteadyOn imports all valid rows and reports any errors

  • The hazard appears in your register with a BRAG status dot
  • If you set a review date, SteadyOn will flag it amber/red as the date approaches
  • You can raise corrective actions from the hazard detail page